More power to Hambantota
Walter Liyanaarachchi
Hambantota District electricity demand will be met by the end of the
year providing 40,000 new connections as planned in 2007.
This includes all the difficult and remote areas which were ignored
in the past due to various reasons.
Realising that mega and small-time development projects were coming
up in the District and taking into consideration the toiling peasants in
the remote areas of the Hambantota District, Ports, Aviation and
Shipping Minister Chamal Rajapaksa in collaboration with President
Mahinda Rajapaksa had decided to formulate the special project Lighting
Sri Lanka Hambantota District in 2006.
The objectives under the project have been successfully accomplished
by meeting the stipulated targets, said Lighting Sri Lanka Hambantota
District Project Director, S. Bogahawatte. Due to the dynamic workforce
in the District and the assistance of efficient and dedicated engineers,
the challenge could be met. In 2006 the power supply to Lunugamvehera
was 36 percent, Weeraketiya 46 percent and Katuwawela, 26 percent. But
today the project could enhance the supply upto 90 percent, 85 percent
and 80 percent respectively, Bogahawatte said.
The demand to start minor industries with self-employment
opportunities has increased considerably recording a marked improvement
in upcoming new industries.
The project had been formulated with the primary objective of
achieving 100 percent customer reach in the District. This means that
all households in the Districts will have access to electricity network
within close proximity so that electricity connections could be obtained
by them at a nominal cost. Related scope of work includes expansion of
electricity supply connections to 40,000 additional customers, he said
Upgrading the network capacity to accommodate future growth,
improvement of reliability and quality of supply to all customers,
improvement of operational efficiency (loss reduction) and energy
conservation are other objectives of the project.
The electricity supply service in Hambantota District could not be
considered satisfactory from the customer point of view in 2006. It was
estimated that about 30 percent of the consumers in Hambantota District
were affected by low supply voltage levels during peak hours. The
reliability of the network did not meet the customer expectations due to
frequent failures caused by long or overloaded distribution lines and
operation and maintenance issues.
The reports indicate that the average duration of loss of supply per
consumer per year was estimated to be 24 hours. It is evident that the
reliability of supply has a significant impact on the economy as the
service sector is the second predominant economic sector of the
district. But due to the prudent step taken by the government by
formulating this project such weaknesses could be eliminated,
Bogahawatte said. |