Electricity for liberated areas
Wasantha Ramanayake
The electrification along the Omanthai Mankulam road had been
completed at a cost of ten million rupees, a Power and Energy Ministry
official said.
According to the official all the three zones of the Menik Farm had
been provided with electricity at cost of Rs. Six million. Further the
Ceylon Electricity Board has spent over Rs. five million to provide
Padaviya hospital with electricity.
Under the Uthuru Vasanthaya program of the President, Power and
Energy Minister W.D.J. Senevirathne has given instructions to the CEB to
launch a program to provide electricity to all the villages in the
Northern Province, the official said.
The CEB has already set up a 36 MW thermal power plant in Chunnakam,
providing electricity to over 600,000 persons in Jaffna. The plant will
be commissioned by the end of this month the official said.
He added that the World Bank has agreed to provide financial
assistance to the electricity infrastructure development in the
liberated areas in the North and the Japanese Bank for Economic
Co-operation has also pledged to provide financial assistance to
construct a 31 km long new transmission line from Vavuniya to
Kilinochchi and a grid substation in Kilinochchi at a cost of Rs. 1,686
million.
|