Work on water supply project resumes
Samanthi Weerasekara
COLOMBO: Work on the Kandy Adjacent Stage 1 water supply project
which stalled half way will be restarted next month by the National
Water Supply and Drainage Board.
The project will cater to, over 20,000 consumers in areas adjacent to
Kandy city. These will include upper, lower and Central Heerassagala,
Asgiriya, Dangolla, Elhena, Gohagoda Road, Akurana, Kulugammana and
Thelambugahawatta areas.
A spokesman for the National Water Supply and Drainage Board said
work on this project was suspended last year since Rs. 1500 million
allocated for it was fully exhausted.
They are now able to recommence work on this project since another Rs.
3,000 million has been received as Japanese aid.
|