Interim injunction sought against Ceylon Shipping Corporation
refused
Commercial High Court Judge Gamini Amarasekera yesterday issued an
order refusing to grant interim injunction prayed for, by Mercator Lines
(Singapore) Ltd thus holding in favour of Ceylon Shipping Corporation
Ltd, in a case related to the supply of coal to the Lakwijaya coal power
plant in Puttalam.
Mercator Lines (Singapore) Ltd, instituted Action in the Commercial
High Court against Ceylon Shipping Corporation Ltd and Lanka Coal
Company (Pvt) Ltd, for the alleged wrongful termination of a contract in
relation to the transportation and lightering of Coal required for the
Lakwijaya Coal Power Plant in Puttalam.
Mercator Lines (Singapore) Ltd pleaded that the dispute was to be
referred to Arbitration but nevertheless sought Injunctive relief
restraining the Ceylon Shipping Corporation Ltd, from giving effect to
the letter of termination and/or contracting with a third party and
sought a further Injunction mandating the Ceylon Shipping Corporation
Ltd to perform the Contract until the arbitral tribunal was properly
constituted and the Plaintiff Mercator Lines (Singapore) Ltd is able to
move for interim relief there.
Counsel for Mercator Lines (Singapore) Ltd, Dr. Harsha Cabraal PC on
October 12, 2012 informed Court that he is not supporting the
application for Enjoining Orders, when Faiszer Musthapha, PC Counsel for
the Ceylon Shipping Corporation Ltd sought to resist the same.
It was agreed that the inquiry in respect of the Interim Injunctions
be disposed expeditiously and at the inquiry Counsel Faiszer Musthapha
raised several objections on behalf of the first defendant Ceylon
Shipping Corporation Ltd, against the granting of injunctive relief
including that the purported dispute of termination is not a matter
agreed by the Parties to be submitted to Arbitration and hence the
relief sought is not tenable in Law, that Mercator is not entitled to
seek specific performance of an agency contract by way of injunctive
relief, that the appropriate relief for the Plaintiff would be damaged
if at all, that the Plaintiff is not entitled to interim relief because
it has breached the principle of utmost good faith in suppressing the
several instances that the Plaintiff was in breach of the Agreement and
that grave and irreparable loss would be caused to the Ceylon Shipping
Corporation Ltd who is primarily responsible for the procurement of coal
in as much as 20 percent of the total supply to the National Electricity
Grid could be affected. Faiszer Musthapha appeared with Farman, Cassim,
Isuru Balapatabendi and Tharaka Nanayakkara for the Ceylon Shipping
Corporation Ltd instructed by M/s Murugesu and Assocaites and Dr. Harsha
Cabraal appeared with Buddhika Ilanganthilake for Mercator Liens
(Singapore) Ltd, instructed by M/s Neelakandan and Neelankandan.
|