Upper Kotmale Project:
Nearly 80 percent work complete
Nadira Gunatilleke
Nearly 80 percent of the construction work of the Upper Kotamale
Hydro Power Project has been completed. The project will add 150 MW of
electricity to the National Grid by the end of this year, a Power and
Energy Ministry spokesman said.
According to the spokesman, the installation of power generating
machines is in progress. machine parts have been imported from a
Japanese company.
The machines are being installed under the supervision of the
Japanese company which handle the contract.
Once completed, the project will add 409 MW of electricity to the
National Grid annually. Japan International Bank for Corporation (JIBC)
provided a loan of Rs 34 billion for the project.
The loan is to be paid within four years with a 10-year relief
period. |