Norochcholai coal power plant:
Major icon of wonder nation
Ariya Rubasinghe
Construction work on Phase one of the
Norochcholai coal power plant is almost completed and it will be
declared open by President Mahinda Rajapaksa on February 10
Under Phase One, Norochcholai Coal Power Plant project will generate
300 mw, which will amount to 17 percent of the national power
requirement and it will be connected to the main grid at Veyangoda. The
initial plans for establishing a coal power plant to overcome the
impending power shortages in Sri Lanka was conceived in early 1970s and
it was planned to establish this plant in Trincomalee, taking into
consideration the port facilities available in Trincomalee for shipment
of coal. Even some engineers and technical staff of the Electricity
Board were sent on foreign scholarship to familiarize with the new
technology.
Work on phase one of the Norochcholai coal power plant is
nearing completion. File photo |
Later-on Trincomalee as a site for this project was abandoned due to
the intensified terrorist activities in the region and it was decided to
establish this project in Norochcholai instead. Accordingly it was
planned to commence this project in the early 1980s.
However, due to political expediency and the value of votes becoming
more important than development of the country, similar to the Upper
Kotmale Project, this project was also totally abandoned citing lame
excuses such as environmental pollution, resentment of some communities
etc. Instead, politically affable private sector firms were allowed to
generate electricity using diesel at a high cost and sell power to the
Electricity Board with substantial profit, thereby making electricity a
burden to the ordinary masses, and even to many industries. Due to these
politically motivated decisions Sri Lanka has lost about two billion
rupees per year all these years.
Visionary decision of President
Upon becoming President in November 2005, President Mahinda Rajapaksa,
for whom the interest of the Motherland is second to none, took the bold
and visionary decision to implement all power projects abandoned for
political reasons and construction of the Norochcholai plant received a
new birth in 2006, upon successful negotiations with the Chinese
Government to finance this project. The plant is being built at a cost
of US $ 455 million on a concessionary soft loan from China facilitated
by China’s EXIM bank. The main contractor of the project is China
National Machinery Import and Export Corporation.
Generate 900 mw upon completion
The total project is being implemented successfully and will generate
900 mw upon completion of all the three phases. Over 90 percent of the
Phase One of the projects has now been completed. All 80 odd families
displaced by the project have been settled in comfortable abodes with
all amenities without disrupting their employment avenues and social
life. Those who were engaged in the fishing industry have been provided
fishing boats and gear and plots of land amounting to two and half acres
for cultivation during the off fishing season.
It is real wonder
It is a beautiful sight to see that these families have cultivated
various kinds of vegetables and tobacco in these lands and particularly
the womenfolk tendering their plants. Test firing of the project was
successfully carried out on November 17, 2010 in conjunction with the
second swearing-in of President Mahinda Rajapaksa.
The total project site covers 95 hectares. Fixing of generators,
conveyor belts for transport of coal, cooling plants, coal crushers,
water purification plants, filtering mechanisms have been completed and
the machinery is being tested at present. It is a real wonder to observe
the plant completed and the machinery is being tested at present. It is
a real wonder to observe the plant function and this plant reaffirms the
possibility of making Sri Lanka becoming the wonder nation of the Asia,
as envisaged by the President.
Arrangements have been made to get coal for this project from
Indonesia due to Indonesia’s close proximity to Sri Lanka and low
Sulphur content in the Indonesian coal. It has been found that
Indinesian coal is cheaper than Australian, South African and Chinese
coal, the other major coal producing countries and the coal extracted in
India has high Sulphur contents and is hazardous to the machinery.
Seven million tons of coal
The plant will require seven million tons of coal for a period of
three months and the coal yard has the capacity to stack this quantity
as during three months of the year due to windy and stormy conditions in
the sea, shipments cannot be made during that period. Already the coal
yard is stacked with sufficient quantities of coal for the commercial
operation of the plant by early next month.
The ships carrying coal will be anchored 45 km away from the shore
due to sea near to the shore being shallow and it will then be
transported to the yard in barges. Each shipment could bring 65,000 tons
of coal and a barge can carry 5,000 tons in each trip to the shore.
The purchase of coal is being handled by the Lanka Coal Limited and
the shipping will be handled by the Sri Lanka Shipping Corporation.
Already there are three barges and three tugboats to handle the
transport activities and it is expected to increase the number of barges
shortly.
The coal will be crushed to about 10 mm particles and the waste will
be separated. The Plant also has the facility to extract Sulphur Dioxide
and Nitrogen Dioxide containing in the coal.
Also it has a filtering mechanism to filter the coal ash and store
them separately. Coal ash can be used for cement manufacture and filling
purposes and presently negotiations are under way with cement
manufactures to sell this coal ash for cement manufacturing.
Pumping seawater
The generators will be activated by steam and the Plant is equipped
with a complete process of pumping sea water, filter it to avoid
unsuitable particles including fish getting into the system, extract
minerals in the sea water, produced purified water and use to generate
steam.
The coal helps ignite the burners and heats the water to produce
steam. The whole Plant is environmental friendly and it has a windshield
covering the whole length of the coal conveyor belt preventing coal
ashes mixing with the environment.
All infrastructure work of the project, including construction of the
access road is being financed by the Sri Lankan Government outside the
funds obtained from the Chinese Bank.
The construction of the access road from the Palavi-Kalpitiya highway
is also nearing completion.
A media tour to the site was organized by the Media Centre for
National Development of the Mass Media and Information Ministry and the
officials at the site including the Senior Project Director W.D.N.
Xavier, Project Director Electricals P C C Perera, Project Director
Mechanical Lokubalasuriya, Project Manager Boiler and Coal handling A P
A De Vas Gunawardene and the Site Project Manager of the main contractor
China Machinery and Equipment Import and Export Corporation, Wong Ludong
apprised the media team about various aspects of the functions involving
in the operation of this project.
The writer is Media Centre for National Development Director General,
Mass Media and Information Ministry
Courtesy: Mass Media and Information Ministry
|