‘Lighting up’ the lives
Dharma Sri Abeyratne
With
a view to light up every Sri Lankan household by 2012 and meet the day
to day increasing demand in electricity, President Mahinda Rajapaksa
drew special attention on the electricity sector through Mahinda
Chinthana. Lighting up whole of Sri Lanka is the focus.
Development work in progress |
In accordance with Mahinda Chinthana, the government of Sri Lanka has
set a target to provide all households with electricity by 2012 while
allocating billions of funds for the development of the sector. However,
over 80 percent of the households in the country have already been
supplied with electricity through mega power projects that have been
implemented under a long-term infrastructure development plan.
Lighting up every home
Setting of a target to provide every household with electricity is a
clear indication that the Government has taken every possible step for
the well-being of people.
Actually that is a great challenge when most of the countries in the
world are facing with severe energy crisis or will face it in the
future, Even though Sri Lanka is in a satisfactory position since Sri
Lanka has taken many steps to get rid of a probable energy crisis in the
future.
The forecast made by the CEB on the growth of electricity demand in
the country, projects a growth between 7 to 8 percent annually in the
next decade. Due to the rapid growth in some sectors of industry and the
accelerated effort in electrification, the demand may increase than
predicted.
Under this program the government has implemented 32 projects in
respect of the power and energy sector during 2006 to 2010, just within
four years. The government has allocated millions of funds for these
projects including two atomic energy base projects.
Norochcholai coal power plant |
Kerawalapitiya Combined Cycle Power Plant Project has already been
commissioned in March 2010. The power plant adds 300 MW to the national
grid. The government has allocated Rs. 36,823 million for this project.
The objective of launching the combined cycle power plant was to avert a
major power crisis in 2008 which would have severely hampered prospects
for development of the country. The total projects cost was Rs 36,823
million funded by the government.
The completion of such mega power project with the expertise of local
engineers is a victory for the country in its journey to achieve
economic prosperity. Moreover the project was completed within a record
two year period.
Strengthening Dams
The construction of Upper Kotmale hydro power project is scheduled to
be commissioned by December 2011 since around 70 percent of the
construction has been completed by now. The project will add 150 MW to
the national grid. With the financial assistance of JICA Ceylon
Electricity Board has allocated Rs 37,269 million for this project. The
construction of the longest tunnel among power projects in Sri Lanka has
been already completed under the Upper Kotmale Hydro power project.
A dam has been constructed across the Kotmala Oya at Talawakele close
to the Talawakele town area. The hight of the dam is 35.5 metres and it
is 180 metres in length. The Upper Kotmale underground power house is
located at Niyamgamdora. Water will be carried through the longest
tunnel to the underground power house from the reservoir.
The Puttalam Coal Power project is also a mega power project which
will produce 900 MW to the national grid. The Coal Power project
consists of three 300 MW generating plants is being constructed at
Norochcholai in the Puttalam District.
The first phase of the project is under the final stage and it will
be commissioned by 2011 adding 300 MW. Under the second phase another
600 MW will add to the national grid. The total project cost is Rs
154,790 million and China financially assists to the project providing
the total project cost. No sooner completing the first phase the second
phase of Puttalam Coal Power project will commence.
Hydro power plant expansion
After receiving the Cabinet approval the construction of the
Broadland Hydro power Project (BHP) which is the last of the series of
hydro power plants of Laxapana Hydro power complex will commence with
immediate effect. The project is now at the tender stage. The
construction of the BHP will be completed by the end of 2014. The
significant of the project is that the project can prevent carbon
emission by 86,000metric tons per year.
The state can earn US $ 2.4 million per year through carbon trading.
The project will have an installed capacity of 35 MW and expect to
generate 126 Gwh of electrical energy annually. The Broadland Hydro
power plant will utilize water of the Kelani river will be built near
Kithulgala at a cost of Rs 9,348 million.
Infrastructure development programs
In addition the Government spends Rs 12,528.26 millions on
rehabilitation three power stations. Under this Ukuwela Power Station
(40 MW), New Laxapana (100 MW) and Wimalasurendra Power Station (50 MW)
and Old Laxapana Power Station (50 MW) are being renewed.
The renovation of Ukuwela power station will be completed by March
2011. Rehabilitation of New Laxapana and Wimalasurendra will be
completed by January 2013 while the rehabilitation of Old Laxapana will
come to an end by June 2013. Under the infrastructure development
programs connected to the power and energy sector several projects have
been implemented. Trincomalee Integrated Infrastructure Project and
Colombo City Electricity Distribution Development Project are among
them.
The allocation for Colombo City electricity project is Rs 10,641.9
million while Euro 2.45 million has been set apart for the Trincomalee
Integrated Infrastructure project. Both projects are in progress.
Colombo city project is scheduled to be completed on December 31 this
year. Under the Trincomalee project more than 38 Km of electricity line
will be constructed. Under the Colombo project many development
activities are under way such as the construction of 8,086 km of 123 KV
underground power transmission line from Kelanitissa Grid Substation to
Kolonnawa Grid Substation, Construction and Rehabilitation of
distribution system, establishment of distribution control system and so
on.
Coal power project
The Trincomalee Coal Power project also known as Sampur Coal Power
Station is also among the major projects in power and energy sector in
the country. The large coal-fired power station is currently under
construction in Sampur, Trincomalee. The MOU for the first 500 MW phase
was signed in 2006 between the government, Ceylon Electricity Board and
National Thermal Power Corporation Ltd (NTPC) of India.
The coal power project will provide the national grid with 500 MW by
2012 under its phase one. The construction of the first phase is being
carried out by the NTPC under the supervision of CEB. The government
allocated Rs 56,000 million for this project. After commissioning the
first phase, the construction of the second phase which will be
completed by 2015 will commence.
Three projects for transmission line development have been
implemented at a cost of Rs 11,717.12 million. Under this, the
construction of 22KV Transmission Line from Kerawalapitiya to Kotugoda
has already been completed while the Transmission line to Vavuniya to
Kilinochchi will be completed by 2012. The construction project of 67.2
Km transmission line from Kilinochchi to Chunnakkam will be commissioned
by 2013.
Under the theme ‘Clean Energy and Access Improvement’ several
projects have been implemented with a view to protect the environment
while achieving better efficiency in transmission systems. Accordingly,
the government has initiated several projects such as modernizing the
system control unit of the CEB, strengthening grid substation,
strengthening transmission lines, augmentation for renewable energy
projects and so on.
Atomic Energy Plants
All these projects are scheduled to be completed in 2013. With the
financial assistance of Asian Development Bank, the government has
allocated Rs 14,955 million for these projects. In addition to those
projects two Rural Electrification Projects are in progress at a cost of
US $ 138.5 million. These projects will be completed by 2012.
In line with the ongoing Uthuru Wasanthaya, Negenahira Navodaya and
Uva Udanaya programs, several electrification projects have been
implemented such as Kegalle District Lighting Sri Lanka project, Eastern
Province Lighting Sri Lanka project (Trincomalee, Batticaloa), North
Central Province Lighting Sri Lanka Project, Lighting Sri Lanka Projects
for Kandy, Ratnapura, Kalutara, Southern Province and Western Province.
All these projects are scheduled to be commissioned by 2012.
The Atomic Energy Authority of Power and Energy Ministry is going to
implement two projects base on atomic energy at a cost of Rs 1,012
million. With the financial assistance of International Atomic Energy
Agency (IAEA), a Multi-purpose Gamma Irradiation Facility (MGIF) centre
will be established. All exporters such as medical gloves and spices
will be benefited.
This project will be carried out under Randora investment program
which has been prepared base on Mahinda Chinthana. As the second
project, National Centre for Non-Destructive Testing (NCNDT) will be
established with the assistance of IAEA.
Support for low income families
Meanwhile the Power and Energy Ministry introduced Viduli Athwela
program which assists low income families to get the electricity
connection. Ceylon Electricity Board together with Samurdhi Bank carry
out the Viduli Athwela, the financial assisting program aiming to assist
every family to get the electricity connection from national grid.
Through the program, the Samurdhi Bank, will grant a soft loan up to
Rs 30,000 maximum. After a six month grace period, the loan can be
settled in 48 installments, Power and Energy Minister Patali Champika
Ranawaka Said.
Low income families, especially Samurdhi recipients will be benefited
by Viduli Athwela because the low income situation has become a
hindrance for obtaining the electricity supply since a considerably high
initial payment has to be made when obtaining the electricity connection
from CEB. As a remedy for this financial drawback, the Viduli Athwela
program was introduced, the Minister added.
The Minister further said that electricity tariff in the country is
high. “Our aim is to control and bring down the high electricity tariff
to an affordable amount while providing every household with
electricity,” Minister Ranawaka noted. |