Upper Kotmale Hydro Power Project - pillar of energy
sector :
Making Lanka wonder of Asia
In line with Mahinda Chintana Power and Energy Policy
:
Ariya Rubasinghe
The Upper Kotmale Hydro Power Project has
invigorated the life standards of the people in the Talawakelle and
surrounding areas. This project which was to be launched in the 1980s,
never saw the day of light due to political expediency and various other
reasons and intimidation, until President Mahinda Rajapaksa came to
power in 2005 and took the bold decision to proceed with the
construction of this project, regardless of
|
Upper
Kotmale project tunnel |
political pressure or otherwise and in line
with the pledge given under the Power and Energy Policy in the Mahinda
Chintana ‘to build coal and hydro-power projects expeditiously’
The Cabinet of Ministers took a decision on April 7, 2005 to
construct the Upper Kotmale Hydro Power Project. On July 27, 2005 the
contracts relating to the preparatory work was awarded to the Maeda
Corporation of Japan. Thus started the launching of this massive Hydro
Power project, the third hydropower project in Sri Lanka, the other two
being Pahala Kotmale and the Kukuleganga Hydro Power projects.
The total estimated cost of the project amounts to 384 million US$ of
which 297 million US$ have been provided by the Japan International
corporation Agency (JICA) as a project loan with 10 years grace period
and repayable in 40 years at 0.95 percent interest. Upon completion the
project will add 150 MW electricity supply to the national grid.
Since then the project has proceeded smoothly surmounting all
obstacles providing a ray of hope to the people of Talawakelle, Kotmale
areas and progressing forward as a pillar of the energy sector that
would become one of the key factors making Sri Lanka the wonder nation
of the Asia.
Infrastructure development
By end of August 72 percent work of the project had been completed.
Along with the project the government has carried out many other
infrastructure construction work which include construction of nearly
400 housing units for resettlement of families who get displaced or
affected by the project, building modern Schools, building a Cinema
Theatre, and construction of government buildings and facilities
required for providing educational, medical, administrative and other
services.
The project has been divided into five categories and has been
awarded to different Japanese contractors. Progress on preparatory work,
main civil works and hydro mechanical works are nearing completion while
over 50 percent of the work related to electro mechanical work and
transmission lines have been completed.
A group of media personnel organized by the Media Centre for National
Development of the Ministry of Mass Media and Information visited the
project sites and locations recently was able to obtain first-hand
knowledge of the work being carried out, facilities provided, sentiments
of the people resettled and make physical visits and observations at
various locations of the project.
|
Entrance to
the main tunnel |
Under the preparatory work construction of new access roads with
drains, culverts and bridges have been completed. This includes
construction of a new 33 km road connecting A-5 (Peradeniya to Nuwara
Eliya Road) and A-7 (Awissawela to Nuwara Eliya Road) named Tawalantenne
Road.
This road has 150 culverts, seven minor bridges and I major bridge.
A-3 storied Office Complex has been built for housing the Talawakelle
Urban Council.
The Talawakelle Tamil School had been functioning on a dilapidated
old tea factory building and had not seen repairs for ages. Since this
structure comes under the area that will be inundated and also to serve
the settled families, the project has built three classroom complexes of
three stories each, which will now have facility for students in the
area to study from Grade One to Grade 13. The school complexes will have
52 classrooms, six laboratories, I library, one computer centre, one
auditorium, a canteen, and principal office and staff room.
Resettlement of people
The most glaring and the most picturesque site was the green colour-roofed
housing units dotting as several groups in the adjoining high elevated
areas. This includes 495 housing units, 33 shops, six workshops, six
libraries, three kovils and two churches.
There had been 489 families who were resident in the Upper Kotmale
Hydro Power Project Area prior to commencement of the project.
Many of them were living in tin-roofed line rooms which had one
verandah and a room with no separate kitchen or bathroom facility,
forced to use one bathroom by several families.
In fulfilling the government’s promise to provide them better housing
facilities, the new modern housing units have been constructed by the
project and all affected people have been settled.
These people who had been living in the nine settlements of
Kumaragama, Devisiripura, Talawakelle, Ratneelakele, Middlton Bar,
Middleton Division, Walkers. UC Scavengers compound and Nanuoya Division
have been resettled in six settlements, allowing integration on their
own and allocating housing units from six types of houses based on land
they used to occupy previous starting from 0-400 sq.ft. These housing
units have been provided with all amenities including water,
electricity, light fixtures and ceiling fans.
The housing units also range from two- five bedrooms with bathrooms,
halls, kitchen etc, and each housing unit is built on seven-ten perches
land area.
Home gardening
|
Underground
power station |
Seventy-five percent of the people resettled in these new housing
units are Tamils and the rest 22 percent are Sinhalese and three percent
Muslims. Many of the occupants have taken to home gardening as well
around their new dwellings and have planted various types of flowers,
and vegetables such as salad, beetroot, tomato, beans, carrot, brinjal
and radish.
To compensate those who were growing vegetables in the previous
settlement areas 42 plots of land have been provided to them to grow
vegetables. To facilitate the occupants of the new houses to meet their
day-today purchasing needs two cooperative shops have also been
established in addition to shops provided for those affected.
Residents interviewed by the media groups expressed their happiness
about getting such modern housing units, which some of them said they
could have never built or dreamt of having on their own, and were
grateful to President Mahinda Rajapaksa for undertaking to built the
Upper Kotmale Project which had been almost abandoned due to political
expediency and other reasons and providing them all the facilities they
require.
Among the other construction work include a rest house, a playground,
and a modern Cinema Hall to replace the wooden planked Cinema Hall that
existed in Talawakelle.
Sri Lanka’s longest mountain tunnel
The icon of this massive project is the 13km long 5.8m width tunnel
which runs cutting through the Talawakelle-Niyamgamdora mountain range.
The drilling of the tunnel, the major work of the project has been
completed and the concreting of the floor is being carried out.
Travelling through this tunnel was a fascination journey for the media
crew.
|
New housing
scheme. Pictures by Sudam Gunasinghe |
Despite comments by certain cynics that the tunnel route is not hold
water and would collapse, the engineers confirmed that the entire tunnel
route was found to be consisting solid base rocks and in addition to
this filling of intermittent areas with reinforced concrete has also
been done. Construction of Concrete Gravity Dam of 157x35x7m and the
surge tank of 12m diameter and 94m height, as well as construction of
the under group power house complex and switchyard are presently under
way 90 percent of the construction of the Dam has been completed.
The intake of water will take place at Talawakelle, and after passing
through the tunnel, would spread into two at the power house area to
provide the force required to generation of power by turbines and then
will be outflawed at Niyamgamdora tunnel exist to the pond area to
connect with the Kotamale Oya.
Several Sri Lankan Engineers are working with dedication filled
national spirit along with their Japanese counterparts to expedite the
project and make it a success. Since the Electro Mechanical Equipment,
and Transmission related work are bound to take some due to the
sophisticated nature of this part of the project, the project is
expected to be completed by end of 2011.
The writer is the Director Media and Information Ministry, Media
Centre for National Development
|