Self-sufficiency in electricity in next 10 months:
Era of bottle lamps will be ended
Ariya RUBASINGHE
Electricity is an essential component for development of a nation.
Politicians in the past paid scant attention to develop this sector and
major projects envisaged to develop electricity supply was kept in
abeyance for political reasons. This resulted in Sri Lanka experiencing
a huge power crisis and this developed to a critical extent in 2000
forcing the Electricity Board to curtail power supplies for several
hours each day, compelling many industries to curb their production
activities and incur heavy loses. Continued power cuts were also one of
the factors that contributed to the fall of PA Government in 2001.
Kerawalapitiya power plant |
Ranil Wickremesinghe Government which assumed office in 2001 pledging
normalization of electricity supplies as one of its promises however did
not address the core issue of implementing the stalled power projects
and take long term measures to end the crisis. Instead, they attempted
to find solace through the private sector thereby rewarding their
political patrons, contravening even Tender Procedures, to set up small
scale power generating units and sell the electricity so generated to
the Electricity Department. This was a costly exercise by which the
Department paid Rs 35-40 per unit and sold it to the customer for Rs
10-11, incurring a huge loss. The Department is yet struggling to
recover from the heavy losses made due to this myopic measure. For
political reasons and for fear for of losing votes they failed to take
bold decisions for implementing Norochcholai and Upper Kotmale power
projects.
President Rajapaksa assuming office in 2005 took the much needed bold
step to implement the major power projects regardless of political
consequences. Due to this wise decision three major power projects,
Kerawelapitiya, Norochcholai and Upper Kotmale are under construction
and preliminary work relating to another project at Sampur has been
completed.
Electricity to a major part of Sri Lanka is supplied through the main
transmission grid in Veyangoda connected to major power projects
throughout the island, and through substations located in many parts of
the country. However, these facilities can only meet 85 percent
electricity required by the household and the balance requirement is met
by the off-grid small scale power plants established in various parts of
the country. These plants use renewable energy technologies such as
mini-hydro, solar, wind and dendro technologies.
Transmission and distribution losses through the main transmission
lines amount to about 12 percent of the power generated. Steps have been
taken to curtail this loss by expanding the capacity of the main
transmission lines. The existing 132 Kv transmission lines are being
replaced with 220 Kv and 400 Kv lines. The Asian Development Bank is
funding this project and out of the 160m US$ allocation 100m US$ will be
received this year.
The implementation of following transmission development activities
is expected to ensure a reliable power supply and reduce transmission
losses of the national grid. These work will include, construction of
Katunayake Grid Sub - Station, improvement of Valachchenai Transmission
Project, augmentation of Colombo A Grid Sub-Station, augmentation of
Colombo 1 Grid Sub-Station, Installation of 220 Kw/132 Kw inter-bus
transformer at Rantembe Power Station, and installation of the 3rd220 Kw/132
Kw transformer at Biyagama.
The private sector is also being encouraged to set up small scale
power projects using renewable energy technologies, to minimize the
dependence on oil and gas. In this regard land has been allocated in the
Puttalam district to establish power plants utilizing windmill
technology. Similarly plants using hydro-technology will be established
in areas where there is abundant water flowing from small waterfalls in
the hill country area.
With these development work in hand the Electricity Board is planning
to make the country self sufficient in power supply within the next 10
months although it was earlier targeted to be in 2012, disclosed M.M.C.
Ferdinando. He said with the commissioning of major projects small power
projects using oil and gas will be closed down. Also, the era of Bottle
Lamps will be ended and electricity which was a luxury denied to
majority of the population living in the rural areas will become a part
and parcel of their daily life.
Also, the Board have reconstructed the old Lakshapana and Ukuwela
hydro power projects with the capacity of 215 MW. This increased the
power capacity which was 2400 GW in 2005 to 2690 GW in 2009. The numbers
of electricity householders have been increased 4.33 million in 2009
from 3.90 million in 2005. The percentage of number of householders with
power supply increased to 84 percent in 2009 from 76.7 percent in 2005.
In addition to this, 7,600 village level small scale Electricity
Development projects have been implemented under various projects such
as Gama Neguma, Maga Neguma, Eastern Udanaya and Rajarata Navodaya.
The Electricity Board has a sufficient workforce to handle laying
transmission lines and attend to repairs and other requirements
throughout the island. The Board has provided training to several
thousand youth in the rural areas thereby alleviating unemployment.
Kerawalapitiya Power Plant
The Kerawalapitiya power-generation project is the second largest
thermal combined cycle power plant. It is a Government/Private Sector
joint venture. The Private Sector partner is Lanka Aloka AB (Pvt)
Limited. Arc Developments International (Pvt) Limited is an Australian
registered company and the major partner in Lanka Aloka.
To be continued
(The writer is Director General, Media Centre for National
Development) |