Interventions in Fertiliser Manufacture
Calyanatissa GUNAWARDHANA
Way back in the 1970s the Sri Lankan Government, “in its great leap
forward” towards industrialisation embarked on numerous industrial
ventures in the petrochemical sector, priority was accorded to the
manufacture of urea.
Naphtha, was readily available from the oil refinery at Sapugaskanda,
which in the 1970s found no application within the country and at best
had to be exported. Thus, the concept of manufacture of urea based on
naphtha as the feedstock was an acceptable proposition.
Urea plant
The urea plant was installed and commissioned by the multinational
Kellogg of U.S.A. at a cost of US$ 171. It took nearly 4 years from the
date of launch of construction to commissioning of the project. The
plant had a capacity of 545 tonnes per day of urea and 940 tonnes per
day of urea. The plant operated for 4 years from 1982 to 1985 and
thereafter the production was suspended.
Rich paddy harvest |
The suspension was triggered by poor counterpart support and gross
mismanagement, a common malady in the public sector. The project was
infested with ‘post-masters’-bureaucrats who held to their posts without
recruiting experts in the field, a common malady seen in the state
sector even to this day. It was misinterpreted as an economic failure.
This was partly attributed to the high capital costs primarily as a
result of the manoeuvres made by vested interests. Ironically, the Sri
Lankan government did not introduce legislation to protect the industry
(a facility extended to all other industries in both the private and
public sector at the time), to protect the nascent fertilizer industry.
Used plants
After production was suspended it went under the hammer. Ten
companies did bid to acquire the plant. The bid demand was high due to
the fact that the economics of relying on used plants (which were
available at a fraction of the cost of a new plant) are enormous. The
capital costs for a new plant, the time to complete the project and the
breakdown of installed costs are advantageous and would be less than
half the value of a totally new plant. This has far-reaching impact on
interests on loans, depreciation and return on equity. This is
accomplished without undermining efficiency. If at the time, the
Government wrote off the cumulative debt accrued (up the time of the
sale) then the State Fertilizer Manufacturing Corporation, with
management expertise from overseas could have run it as a viable
project.
The following news feature describes the relocation of the plant in
UAE, 29th July 1996 (Source: ACN).
“.... Southern Petrochemical Industries Corp (SPIC) a company based
in South India is planning a 1000 tonne/day (330,000 tonne/year) urea
facility in Jebel Ali, (an investment zone) in the United Arab Emirates,
based on a plant to be relocated from Sri Lanka.
The Indian company is awaiting environmental clearance from the UAE
government and expects the go-ahead to be given before the end of this
month.
The facility, which will take 24-30 months to set up, is expected on
stream in March 1998. The engineering contractor and technology licensor
will be Kellogg. The facility, designed by Kellogg, was bought second
hand from Sri Lanka.
The Phosphate Fertiliser Project
The first ever rock phosphate project, based on apatite deposits at
Eppawela, was the most controversial project that I ever handled in my
career. The project proper, including the design and construction of the
processing facility was a product of my own, and eventually became (to
borrow Hoffman’s expression) - “my problem child”, and as such, it was
carefully nurtured it.
Apatite deposit
My professional colleagues, with the exception of Willie Herath, tore
me to pieces, yet I emerged unscathed, having accomplished my task. The
apatite deposit ‘discovered’ by Geological Survey’ as projected in the
original plan, was to have proceeded beyond the rock phosphate stage
towards the manufacture of soluble phosphates, (DAP, MAP Single super,
Triple super phosphate etc) but was not to be. (ref. Fertilizer panel -
proposals, Ministry of Planning and Economic Affairs).
The subsequent phase of the phosphate development programme was to
set up a plant to manufacture soluble phosphates.
The project launched by a US Company, came to a premature end, and
numerous other projects centred round the deposit were abandoned, due to
pressure brought about by misguided youth, stage managed by a few NGOs
based in Colombo.
This led to the censure of Sri Lanka as an unreliable platform for U.
S. investments (see. U. S. Dept of Commerce official communiques on the
subject), was little known. The apathy shown by US investors persisted
for years that followed.
The writer is Former Deputy Director, Ministry of Planning and
Economic Affairs |