New project for electricity development in Colombo City
Pathmasekara NISSANKA Rambukkana Group Corr
The Colombo City, the commercial capital of Sri Lanka is fast
developing as one of the main commercial hubs of the South East Asia. In
order to cope up with the expectations of the prospective investors and
business community, upgrading of the infrastructure facilities is a
mandatory requirement.
|
N J C S
Perera
Project Director
CEB Greater Colombo
Distribution project |
If these developments do not take place in time, tremendous hardships
will be faced by the people of Sri Lanka. The Electricity sector is the
most important among these sectors which has a direct impact on the
economic development and the difficulties faced by the electricity
sector has become a national issue.
If the Colombo City Electricity supply is not developed properly, the
effects would be experienced by the entire society as well as by the
economy of Sri Lanka in particular. Under such circumstances, it is the
responsibility of Ceylon Electricity Board to provide a reliable and
uninterrupted electricity supply to Colombo City electricity consumers.
In view of the above, the CEB has already formulated and commenced a new
electricity project aimed at providing a reliable power supply to
Colombo City.
Electricity supplies
The Colombo City Electricity Distribution Development Project
initiated by the Ceylon Electricity Board receives the funds necessary
for the project under a loan agreement signed by the government of Sri
Lanka with Japan Bank of International Cooperation (JBIC) and the loan
amount is Rs 6334 million. It has been envisaged under the project to
replace and refurbish outdated and overloaded electrical switchgear and
underground cables. The customers on the waiting lists for new
electricity supplies would be benefited under these development
activities. In parallel with the project, the JBIC has assisted the CEB
in providing a consultancy service for enabling the CEB to address the
critical issues faced during project implementation.
It has also been possible to obtain the services of experienced local
consultants along with services of foreign consultants which has enabled
to save Rs 172.5 million that would have gone out of the country and
this money is now allocated for further developments under the project,
according to the Project Director of Colombo City Electricity
Distribution Development Project N J C S Perera. The consultancy
services contract has been awarded to the Joint Venture of Tokyo
Electric Power Services Co. Ltd. (TEPSCO) and Electric Power Development
Co. (J-Power). In association with Fichtner GmbH & Co. KG (Fichtner),
Germany. Takazi Izumi, is the Project Manager of Consultancy Services
contract. The process of pre qualification of bidders has been completed
and bids have been invited from the pre-qualified bidders for the
construction work of the project.
CCEDD project
Project Director Sirinimal Perera emphasized the following further in
this regard.
Under this project it would be possible to provide a reliable and
efficient electricity supply to the consumers meeting their specific
requirement. The project has been formulated in the year 2001. The JBIC
has agreed to provide funds for the project. The JBIC will provide
Japanese Yen 5959 million (Rs 4,138 million) and the CEB will provide Rs
2,196 million towards the project cost. Total estimated cost is Rs 6,334
million.
The project works of CCEDD project have been subdivided into four
packages;
Package A: GIS Substations
* Installation of one Bay of 132k V GIS Kolonnawa Grid Substation.
* Installation of ten Bay of 132k V GIS Kelanitissa Grid Substation.
* Upgrading of Primary Substation “C” (33/11k V, 3x12.5 MVA to 132/11
k V), 2x31.5 MVA)
* Control/Protection system for 132kV and 11kV Switchgear.
l Installation of RTU for SCADA control, communication and
telecommunication system.
* Buildings and Services (132kV GIS building and 132kV control and
protection room etc.)
Package B: Design, supply, construction, testing and commissioning of
single circuit of 132kV underground cables:
* From Kelanitissa Grid Substation to Primary Substation “C” with a
route length of approx. 2.0km and
|
Greater Colombo Project Power
Distribution Exchange. Pictures by Pathmasekara Nissanka |
* From Kolonnawa Grid Substation to Primary Substation “C” with a
route length of approx 6.7km.
Cable routes are mainly located within main streets in Colombo City
and crossing a canal, major roads, Railways, etc.
Package C: Construction and Rehabilitation of 11kV Distribution
System in Colombo city and Augmentation of one Primary Substation.
Design, supply, installation and commissioning of following works in
Colombo city:
* Installation/ replacement of 11kV cables: approximately 130km
* Installation of 11kV/0.4kV Compact Distribution Substations:
Approximately 100 Nos.
* Installation of Low Voltage cables: approximately 40 km
* Installation of Feeder Pillars: approximately 200 Nos.
* Augmentation of Primary Substation “H” (33/11kV, 2x16MVA to
33/11kV, 3x16MVA, including the required 33kV and 11kV transformer
control panels and 11kV outgoing panels),
6.Supply and installation/ replacement of 11kV Switchgear panels at
Primary and Distribution Substations: approximately 474 Nos. (Most of
these panels need to be linked with the proposed Distribution Control
Centre under Package-D),
l Installation/ replacement of 11kV Ring Main Units: approximately 50
Nos. (Most of these RMUs need to be linked with the proposed
Distribution Control Centre under Package-D)
Package D: Establishment of A SCADA System including Construction of
Distribution Control Centre
Design, supply, erection and commissioning of following electrical
and electronic works in Colombo City.
* Installation of a SCADA/Distribution Automation System (SCADA/DAS)
including complete hardware & software packages for SCADA/DAS and
Distribution Management System (DMS) functionality, Control Centre
(including building) and data communication systems (fibre optic,
communication cables, power line carrier, radio systems, fixed wireless
and mobile phone system. Etc) to the remote stations.
* Installation of Remote Terminal Units (RTUs) at Grid and Primary
Substations, approximately 10 Nos.
* Installation of Remote Terminal Units (RTUs) at selected circuit
breaker operated Distribution Substations, approximately 100 Nos.
* Installation of Remote Terminal Units (RTUs) at selected Ring Main
Unit operated distribution substations, approximately 50 Nos.
* Installation of communication system for SCADA including
communication facilities to link up with the Transmission System Control
centre.
After the completion of the project the electricity consumers living
in the Colombo city as well as Government institutions. Multi-national
companies and other business enterprises who are directly involved with
development of national economy will be benefitted.
As most of the medium voltage and low voltage switchgear and cables
are presently in an overload condition and almost exceeded their
lifetime, a reliable power supply cannot be provided.
Under the directions of the Project Director, a new Internet website
had been developed for providing the updated information of the project.
All the data relevant to the project can be obtained from this website
www.cceddp.com.
A summary of the project activities is given in the Home Page of
Website. As there are four distinct packages A,B,C and D the individual
package has a dedicated webpage giving information of the particular
package. The "contact us" webpage has the contact information of the
officers and other staff attached to the project. It is also possible to
obtain further information of the project activities by sending on
e-mail to the relevant officers.
|