BP: ‘Static kill’ might do the trick alone
After insisting for months that a pair of costly relief wells were
the only surefire way to kill the oil leak at the bottom of the Gulf of
Mexico, BP officials said Monday they may be able to do it just with
lines running from a ship to the blown-out well a mile below.
Oil leaking after the Deepwater Horizon explosion |
As crews planned testing to determine whether to proceed with a
‘static kill’ to pump mud and perhaps cement down the throat of the
well, BP Senior Vice President Kent Wells said if it’s successful the
relief wells may not be needed, after all, to do the same weeks later
from the bottom.
BP said on Monday that a crucial test ahead of its planned would be
delayed due to a leak and the kill operation will now ‘possibly’ happen
on Tuesday.
“During final preparations to commence with the injectivity test, a
small hydraulic leak was discovered in the capping stack hydraulic
control system,” BP said. “The injectivity test, previously announced to
take place today, will be rescheduled until the leak is repaired.”
The primary relief well, near completion, will still be finished and
could be used simply to ensure the leak is plugged, Wells said.
“Even if we were to pump the cement from the top, we will still
continue on with the relief well and confirm that the well is dead,” he
said. Either way, “we want to end up with cement in the bottom of the
hole.”
Government officials and company executives have long said the wells,
which can cost about $100 million each, may be the only way to make
certain the oil is contained to its vast undersea reservoir. A federal
task force says about 172 million gallons of oil made it into the Gulf
between April and mid-July, when a temporary cap bottled up all the oil.
That number is on the high end of recent estimates that anywhere from
92 million to 184 million gallons had gushed into the sea.
The federal task force says about 206 million gallons total gushed
out of the mile-deep well between the April 20 rig explosion that
triggered the spill and July 15, when engineers placed a temporary cap
on the leaking well. The fleet of boats and other efforts were able to
contain more than 33 million gallons.
The company began drilling the primary, 18,000-foot relief well May
2, 12 days after the Deepwater Horizon rig blast killed 11 workers, and
a second backup well May 16. The first well is now only about 100 feet
from the target, and Wells said it could reach it as early as August 11.
“Precisely what the relief wells will do remains to be seen given
what we learn from the static kill,” BP spokesman Daren Beaudo said.
“Can’t predict it for certain.”
Retired Adm. Thad Allen, the Government’s point man on the spill
response, said Monday that the focus now is on making sure the static
kill is successful. But he cautioned that federal officials don’t see it
as ‘the end all, be all until we get the relief well done.’
Condition of well unknown
One of the biggest variables is whether the area called the annulus,
which is between the inner piping and the outer casing, has sprung an
oil leak. Engineers probably won’t be able to answer that question until
they drill in from the bottom, he said.
“Everyone would like to have this thing over as soon as possible,”
Allen said, adding that they don’t know the condition of the well until
the start pushing mud into it.
The company’s statements Monday might signal that it is more
concerned than it has acknowledged about debris found in the relief well
after it was briefly capped as Tropical Storm Bonnie passed last week, a
Louisiana State University environmental sciences professor Ed Overton
said. Plus, trying to seal the well from the top gives BP two shots at
ending the disaster, Overton said.
msnbc.com
|