The role played by the Power and Energy Ministry:
Future of energy development
Energy development is the main target of the national development
program in the country under the Mahinda Chinthana. The Power and Energy
Ministry has been entrusted with the responsibility of providing
guidance and leadership to meet the electricity requirement while
providing a solution to the looming energy crisis in 2012.
It is a great achievement of the Ministry that, under the guidance of
President Mahinda Rajapaksa, the ability to launch a well-planned
long-term, middle-term and short-term program for energy development to
overcome the national energy crisis which was created due to
non-implementation of timely decisions.
Scarcity of hydro-electricity
The Kerawalapitiya power station- a step to remedy the future
power crisis |
The main problem we encounter in energy development is the capacity
of the hydro power houses being limited to 35 percent of the total
electricity demand. A serious problem experienced by Sri Lanka is the
dependency on fuel powerhouses to meet 60 percent of the electricity
demand of the country. Fluctuation of the production cost per unit in
parallel with the increase of fuel charges in the world market is a
serious problem faced by this Ministry. One unit of electricity
generated at a cost of Rs. 14 has to be sold to consumers at a
concessionary rate of Rs. 10.80.
The Ceylon Electricity Board incurs a loss of Rs. 500 million per day
and this has resulted in creating a severe financial crisis in the CEB.
Construction of coal power plants
The initiatives taken to construct four coal powerhouses under
long-term energy development planning to achieve the target of eight
percent economic growth as stated in the Mahinda Chinthana by providing
electricity at a concessionary rate while overcoming this financial
crisis is a great achievement of the Ministry. Arrangements are being
made to obtain electricity capacity of 3,200 MW from coal powerhouses at
Puttalam, Trincomalee and Hambantota by 2012.
A giant step moved towards the national power development was the
opening of the coal powerhouse at Norochcholai, Puttalam on May 11,
2007, which had been blocked over a decade due to public protests.
The Ministry is taking steps to construct 80 fully furnished houses
at Daluwa, Norochcholai for 72 families displaced due to the
construction of coal powerhouse, which is the first ever coal powerhouse
in the history of Sri Lanka and to improve the infrastructure facilities
of the area. Widening of the road to Norochcholai Powerhouse 18 km along
the Palavi Junction to Kalpitiya as a 60 ft road has already commenced.
Development of the road to the powerhouse and to provide electricity
have also commenced. Steps have been taken to provide road facilities,
schools, community halls, hospitals and to transform Daluwa into a
developed area. This scheme would be completed by December and 72
families are settled. It has been planned to release electricity
capacity of 900 MW to the national grid and the cost of this project
would be nearly USD455 million.
Upper Kotmale Project
The ability to commence the construction of Upper Kotmale Project
which had been blocked for over a decade due to various public protests
is a giant step towards the energy development.
This project commenced in 2006 and fully furnished houses for 495
displaced families had been built under four segments.
Under the short term energy development solutions, the Ministry
initiated the construction of a powerhouse at Kerawalapitiya which is
expected to complete by 2008. As the Cabinet approval and the LOI
licence have been submitted to Lakdanavi Company Ltd. which is a
subsidiary institution of the Ceylon Electricity Board, its initial
operation commenced in November.
This powerhouse of 300 MW capacity would commence as a diesel
powerhouse at the beginning and would be converted to a gas powerhouse
later. The Ministry has taken steps to construct this powerhouse as a
solution to the imminent power crisis.
The electricity capacity needed to meet eight percent annual increase
of demand for electricity is 150MW. Under the Mahinda Chinthana with the
objective of supplying electricity to all the villages in Sri Lanka, all
those functions to find solutions to the power crisis were taken under
the custody of the Ministry.
The Ministry while encouraging the Ceylon Electricity Board follows
an efficient and productive measures to find solutions to the power
crisis, and to construct small, medium and large scale powerhouses. It
has taken measures to encourage energy management by providing LOI
approval and many energy managers have come forward to make their
investment in the energy sector.
Overall electrification level in 2009 - 85%
|
Status of electrification
Colombo 98%
Gampaha 98%
Kalutara 83%
Galle 97%
Matara 94%
Hambantota 80%
Moneragala 50%
Ratnapura 70%
Nuwara Eliya 86%
Badulla 67%
Jaffna 60%
Kilinochchi 4%
Ampara 67%
Batticaloa 54%
Kandy 79%
Kegalle 79%
Polonnaruwa 69%
Matale 84%
Tromcomalee 56%
Anuradhapura 71%
Kurunegala 76%
Puttalam 83%
Mannar 37%
Vavuniya 62%
Mullaitivu 1% |
Natural energy development
The world’s new trend of energy development has been focused towards
natural gas development. Power generation using natural energies has
commenced in Sri Lanka and the Ministry has drawn its attention to
develop small scale natural energy development such as wind, dendro,
bio-mass, waste sugar canes, solar power as large scale power projects.
The Ministry has focused attention to improve Narakkalliya wind
powerhouse at Puttalam up to 90 MW and the LOI needed for this has
already been granted. The Ministry has provided guidance to improve
electricity of 1MW generated using the waste sugar cane disposed from
Pelawatta Sugar Factory up to 50 MW and arrangements are being made for
this.
A bio-mass powerhouse is being constructed at Muturajawela with the
Western Province Solid Wase Disposal Authority using the garbage
collected from Colombo city and the Ministry has planned to add
electricity of 32 MW to the national grid from this powerhouse.
The Ministry has been taking steps to establish a Sustainable Energy
Authority to develop energy sources by promoting natural energy
development. At this end, steps are being taken to develop 1MW dendro (gliricidia)
electricity capacity to 180MW and to direct people to cultivate
gliricidia by selecting un-cultivated land and to uplift the rural
economy.
It can add the power so generated to the national grid. The Ministry
has focused attention to construct new powerhouse at Embilipitiya,
Moneragala, Hambantota and Anuradhapura in addition to the existing
powerhouse at Walapane. The Ministry anticipates to direct the natural
energy development to a new path by establishing the Sustainable Energy
Authority.
Development of rural electrification
The ability to provide electricity to 78 percent of the population
was a great achievement of the Ministry, but non-availability of
electricity f 22 percent of the population has a negative impact on the
socio-economic development of the country.
China and ADB assisted power projects have been completed to provide
electricity to villages. Under this, 7,400 out of 4,200 power projects
have been completed. The Ministry has opened 80 power projects within
the past nine months. USD 24 million has been spent on this project.
- The Power and Energy Ministry.
To be continued |