Challenges in the North and East construction
industry and possible approaches to meeting them:
Encourage private sector investments
Eng. (Dr.) P. Mervyn Gunasekera
Paper presented at the 22nd Annual Session of the OPA held on October
10, 2009.
With the ending of the three-decade old war in the North and East,
professionals have a responsibility to support the relevant authorities
to build up these areas to not only help to raise the living standards
of the people of the area but also to enhance the economic development
of the whole country.
In the development activities in the North and East areas, the
construction industry will have a major role to play which includes
reconstruction of the damaged structures and facilities, construction of
houses and common facilities such as hospitals, schools and
infrastructure facilities etc.
Development activities
When considering the magnitude of the development activities that
need to be completed, providing the resources and the planning inputs
required to successfully complete these development activities as
scheduled is a challenge. Some of the challenges that the construction
industry faces are: lack of resources such as materials,
skilled/semi-skilled workers (especially in plumbing, electrical,
welding, formwork, steel and metal work, concreting, equipment
operating), plant and equipment and quality testing facilities, etc.
Furthermore, almost all the infrastructure facilities and utility
systems in the North and East are in a disused condition. And also,
before commencing construction work, de-mining the affected areas must
be completed.
One other major challenge that the Government will face is to find
the required capital for development. Even though there are donors and
the loans received may be available to carry out some of the major
activities, the Government too will have to provide a fair share of
financial support for the construction activities.
Therefore, it is necessary to find ways and means of formulating a
comprehensively phased development strategy with milestones to encourage
private sector investments in the North and East, which will be directly
linked to the construction activities so that not only will the
investors be assured of adequate returns on their investments, but also
those investments will pave the path to overcome a number of challenges
mentioned above so that the construction work can be easily planned and
completed as scheduled according to required standards.
The purpose of this paper is to discuss some of the possible
approaches not only to encourage the investment opportunities in the
North and East construction work but also to ensure that the required
facilities are available for consultants and constructors to facilitate
construction industry activities and complete the work as scheduled.
Since most of the construction work in the Eastern Province has been
planned and some of the work has already been completed or/and about to
be completed, this paper concentrates on the construction activities in
the Northern Province.
Present status
In the Northern Province, there are approximately 300,000 internally
displaced persons (IDPs) presently living in temporary camps or with
relatives and friends in other areas. The Government has already started
resettling these IDPs.
It must also be noted that Government buildings and other public
facilities including infrastructure facilities and utilities are
completely or partially destroyed and/or damaged as a result of three
decades of war. Most structures, facilities and utilities are in an
unsuitable condition because of non-existence of maintenance work.
Owing to the absence or paucity of construction activities (other
than the work relating to the war), a limited local skilled/semi-skilled
labour force is available in the area for deployment in new development
activities. It is required to carry out a detailed manpower survey in
the province to support the construction activities. At the same time,
it is necessary to undertake a comprehensive survey of existing local
material sources to ascertain the available quantities and qualities so
that the supply of materials for construction work can be planned
accordingly.
Areas that were under LTTE control are heavily mined. Unless these
areas are totally de-mined, it is not possible to commence any activity
in these areas. The Government, with foreign assistance, is very
effectively carrying out de-mining operations but it is not an easy task
that can be done quickly.
Planning work
The development activities in the war-affected areas, in general, can
be categorized into three stages as stated below:
I. Short-term Development (immediate requirements)
II. Transition Period
III. Long-term Development
Short-term requirements are those that are needed to be done
immediately. The Government has already provided the required basic
facilities but there are issues that need careful attention. It is not
possible to keep IDPs for a long period of time in temporary camps and
therefore, semi permanent facilities need to be provided for a minimum
period (transition period) of one year or more until such time permanent
facilities are made available. It is necessary to design and construct
semi-permanent housing units with basic facilities such as sanitation
and potable water systems so that IDPs can move from the temporary camps
to semi permanent housing units. This is mainly because it will take a
minimum of 2-3 years to plan and build permanent housing units with the
required facilities. When selecting the locations for semi-permanent
and/or permanent facilities it is very important to select places
convenient for IDPs and minimise the environmental impact due to
construction and subsequent use of those facilities. In this regard,
recycling of materials, minimizing of waste, controlling of ground
pollution and preventing mosquito breeding should be on the priority
list.
Strategies for long term planning should be based on the social,
cultural, political and security requirements of the people living in
the area. Furthermore, livelihood development of the people and also
economic development of the area should be integrated with the country's
total development.
It is observed that at present almost all the relevant Government
organizations have planned out their work in the Northern Province. For
example, under the Uthuru Wasanthaya program, "the proposed plan to
rehabilitate and improve highways and to provide support and technical
assistance to improve rural roads in the Northern Province," prepared by
the Ministry of Highways and Road Development, is in two stages. State 1
covers the road projects that could be completed or commenced within the
first 180 days to expedite the relief program. Stage 2 covers a further
3-year road development program in the province to facilitate
resettlement, livelihood development and regional growth. Similarly,
other organizations also have completed or are completing their plans
for contributing to the development effort. At the same time, some
programs are under way with the assistance of donor countries and
organizations, for commencing reconstruction work.
Possible approach
Responsible Unit
The author's view is that it is necessary to establish an Authority
with total regulatory powers to co-ordinate, regulate and monitor the
construction activities in the Northern Province.
Under this Authority, to establish a Planning and Monitoring Unit (PMU)
responsible not only for planning and monitoring all development
activities in the Province, but also responsible for approving
development projects after reviewing the project proposals for
consistency with Government policy and practice.
Detailed planning
The PMU shall prepare a master program incorporating all proposed
construction work in the Province, after obtaining the following
information from the project implementing organizations.
a. Project description;
b. Detailed programs with relevant major activities, their
time frames and estimates;
c. Proposed procurement systems; and
d. Approximate quantities of the required resources and the
time frame for their acquisitions.
In general, the main resources required by contractors are:
- Supervisory Staff;
- Skilled workers (masons, carpenters, plumbers, electricians, steel
workers, formwork fixers, painters etc.);
- Ready-mix concrete;
- Road construction materials;
- Sand, cement, metal;
- Cement blocks;
- Bricks;
- Roofing materials'
- Timber;
- Pre-cast components;
- Reinforcement and structural steel;
- PVC pipes and fittings;
- Plumbing fixtures; and
- Electrical items.
e. Other information that is required for PMU activities.
After obtaining the abovementioned information/data from the relevant
organizations, the PMU should not only use this information/data to plan
and monitor the construction work, but they can also utilize them to
invite prospective investors to Build, Operate and Manage, Support
Industries to provide the required resources, goods and services for the
construction industry.
For example, it is estimated that about 80,000 permanent housing
units are required to provide housing for all IDPs. Constructing 80,000
housing units each having 70 sqm of floor area during the next 1-5 years
will require approx. 20 million bags or cement, 1.2 million M3 of sand
and 4.5 million litres of paint etc.
Resources for other buildings such as, schools, community centres,
commercial buildings, public buildings etc., will also be needed.
Investor guide
It is estimated that when constructing the Northern line from
Vavuniya to Kankesanturai including back line from Medawachchiya to
Talaimannar, Sri Lanka Railways is planning to construct 320 buildings
(Stations, Living Quarters and other buildings). Furthermore, they need
441,750 pre-stressed concrete sleepers to complete the abovementioned
network.
If the PMU can prepare an Investor Guide, without commitments,
providing the above information/data with relevant time frames, that
will be a very effective marketing tool to motivate investors to Invest
in, Build, Operate and Manage Support Industries. Why? Data relating to
the market is available, pay back period and profit can be easily fixed
and risk involved in the investment can be early assessed, then it will
be a very easy task to take decisions.
Possible Support Industries/Facilities that can be set up in the
Northern Province are:
- Ready-mix plants;
- Cement block making;
- Pre-cast concrete components (Hume pipes, slabs, structural
components, fence posts etc);
- Timber stores;
- Testing laboratory facilities;
- Plant and equipment hiring/leasing facilities;
- Warehousing;
- Cement stores;
- Work/repair shops;
- PVC pipes fitting shops;
- Electrical shops;
- Accommodation camps for staff and workers;
Some of the important areas that should be considered when preparing
the "Investor Guide" to Build, Operate and Manage Support Industries in
the Northern Province are:
a. Clearly defined investment opportunities in the
construction industry with their time frames;
b. Develop and establish appropriate regulations (for example,
environmental, safety, security and quality requirements and also price
control of products/services) providing standards that should be
maintained during construction and operations;
c. Permit more than one supplier/producer to set up their
industries in the support industry park, so that the price and service
competiton can be maintained. However, the number of competitors should
not exceed the demand levels; otherwise, investors will be discouraged
to invest their money to provide goods and services;
d. Zoning of Support Industry parks depending on the type of
operations of the industries in relation to environmental impacts;
e. Facilities available for investors and their cost
(electricity, water, road access, security, etc.);
f. Government to provide incentives such as development
grants, tax benefits, low interest loans etc., for investors;
g. Training of locals shall be an integral part of the
industry operation.
Optimising local resource usage
To reduce the construction cost as well as time, other areas that
need to be considered are:
* In Sri Lanka, standard technical specifications are being used
throughout the country for construction activities. It is important to
make changes as appropriate to the technical specifications to
accommodate locally (North and East) available material by doing
necessary design changes. This will help not only optimise the material
usage but also it will cut down cost and time taken for construction
activities.
* When reconstructing roads, railway tracks and other services, the
question is, is to necessary to follow the same old routes or to
consider new routes, which will provide more cost and time effective
construction with direct links to the total development plan of the
North and East. In general, what can be seen is, reconstruction is being
carried out along the same old routes established by British rulers.
The author is a Past President of the Institution of Engineers Sri
Lanka and Past President of Federation of Engineering Institutions of
South and Central Asia. |