Upper Kotmale Hydropower Project:
A development boon
Pathmasekara Nissanka
The Upper Kotmale Hydropower project has a positive impact on the
people in the area while providing opportunities for improved social and
economic development says Upper Kotmale Hydropower Project Director
W.J.C Shavindranath Fernando.
Following are excerpts of the interview.
Where is the project located ?
Constructing the 12.9km length tunnel. Pictures by Pathmasekara
Nissanka |
The project site is situated in the South central mountainous area of
Sri Lanka. It covers the upstream catchments of the existing Kotmale
reservoir on the Kotmale oya, a tributary of the Mahaweli Ganga.
The water of the Kotmale oya will be diverted from the head pond
through the intake, from which the water enters into the headrace tunnel
(about 13 km long). The headrace tunnel conveys the water to the
powerhouse cavern, through the inclined penstock tunnel, where two
Francis turbine units will be installed.
The underground powerhouse is located at the close proximity of
Niyangandora village in the Kotmale Divisional Secretary’s Division.
After passing the turbines, water will be returned into the existing
Kotmale reservoir via a tailrace tunnel. The power generated will be
transmitted to existing Kotmale switchyard through a 220Kv double
circuit line.
What are the important milestones?
1985 - 1987 - Feasibility study under the Japan International
Cooperation Agency (JICA) technical assistance.
1992 - 1995 - Overseas Economic Cooperation Fund (OECF) of Japan
funded the Conceptual Design. Environmental Impact Assessment and the
Final Design.
2000 - Secretary of the Minister of Forestry and Environment gave
final clearance to implement the project subject to the strict adoption
of the proposed mitigation measures in accordance with National
Environment Act No. 47 of 1980. (Amendment Act No. 56 of 1988).
2002 - Loan agreement between the Government of Japan and Sri Lanka
was signed.
2003 - Central Environment Authority (CEA) appointed Environment
Monitoring Committee to evaluate the implementation of the proposed
mitigation measures by the CEB.
Electric Power Development Company Limited, Japan (J. Power) was
appointed as Project Consultant.
2005 - Lot 1 - Preparatory works, contract was awarded.
2006 - Lot 2 - Main civil works, contract was awarded.
What is the project
investment cost? |
Total
project cost: Dollars 384 Million
Local Investment: US Dollars 87 Million
Total loan amount: US Dollars 297 Million
Interest : 0.95 percent per annum
Grace period: 10 years.
Re-payment period, 30 years (Excluding grace period).
|
2007 - Lot 3 - Hydro Mechanical works, contract was awarded.
2008 - Lot 4 - Generating Equipments, contract was awarded
2008 - Lot 5 - Transmission line, birds were flouted
What are the waterfalls affected and
mitigation measures applied by CEB?
Only St. Clair’s fall is affected by the project and it is proposed
to release water intermittently 10 times a day to retain its natural
beauty.
What are the environmental and social
benefits?
The Upper Kotmale Hydropower project provides local areas with a
number of environmental and social benefits. It will also provide more
benefits during its operation phase. While the local social benefits
have been largely confined to the areas around Talawakelle town,
Pundaluoya and Kotmale, wider benefits of watershed management will
extend to the whole of the upper basin.
What are the benefits during the
current implementation phase?
The presence of the project has positive impacts on the local
communities, providing opportunities for improved social and economic
development. It has stimulated the local business growth with
opportunities created by the construction activities.
The following employment opportunities are being provided by the
project
* Skilled construction labour
Project Director
W.J.C Shavindranath
Fernando |
Power Minister
Mahindananda Aluthgamage |
* Unskilled labour
* Domestic staff, canteen staff and other residential facility
support staff
Benefits during the operational phase
The project will provide the opportunity to make significant
improvements to the social and economic environment of the local
communities.
* The business community also expects certain benefits due to local
tourism from the reservoir landscape, attracting people to use
restaurants and other facilities in the town.
* The project will furnish infrastructure development including
roads, bridges, culverts, electricity, telecommunication, water supply
and garbage disposal facilities. These improvements will certainly
enhance.
* The Upper Kotmale Hydropower Project will contribute to the
environment improvement benefits global as well as in the local context.
How does environmental protection and
management take place?
The Environmental Management Plan
Prior to commencement of construction activities in 2003, a
Comprehensive Environmental Management Plan (EMP) was prepared. This EMP
served to provide supporting information to the tender process so
ensuring that the environmental responsibilities of the contractors are
known from the outset.
Establishment of
Environmental Management Office.
An Environmental Management Office has also been established and it
forms part of the project management office. The EMO is staffed by an
Environmental and Resettlement officers.
Compliance monitoring
inspections
Environment inspections are often carried out by a team comprising
environment representatives of the employer (CEB), consultant (J. Power)
and contractors to ensure compliance with EMP requirements.
Establishment of
Environment Monitoring Committee.
In order to evaluate the implementation of the proposed mitigation
measures in the EIA report the Central Environment Authority has
appointed and Environment Monitoring Committee (EMC) in accordance with
the Gazette extraordinary No. 1283/19 of April 10, 2003.
National Environmental (Upper Kotmale Hydropower Project Monitoring)
Regulation No.1. This EMC chaired by the Director General, Central
Environment Authority comprises representative from 23 agencies covering
following fields.
* Plantation
* Tourism
* Agriculture
* National level regulatory authorities
* Non-Governmental Organizations
* Local and regional administration at political authorities
What are the environment safeguard and mitigation measures taken by
Environment Management office of Upper Kotmale Hydropower Project?
* Monitoring of air quality, noise and vibration at construction
sites.
* Surface water quality monitoring of stream of the projects area on
a monthly basis.
* Implementation of recommendation of bio-diversity assessment
conducted by IUCN of the streams impacted by the project.
* Ground water level and surface water discharge monitoring along the
tunnel route on a weekly basis.
* Map out of existing landside and potential areas within the project
foot print in order to mitigate any adverse impact from the project.
* Stream flow measurement and sediment load monitoring.
* Standardized photographic record of St. Clair’s waterfall on a
monthly basis.
What are the measures taken to manage the watershed of Kotmale Oya?
A comprehensive Watershed Management Plan has been prepared by the
CEB and it has been put into action by the project EMO, which comprises
the following activities.
* Gully conservation.
* Conservation-oriented agriculture.
* Increasing the tree cover.
* River bank protection with bamboo tree plantation.
* Tree planting to enhance water table.
* Improvement of poorly manage/degraded tea land.
* Protection of landslide prone areas.
* Fire Protection Implementation of fire belts.
* Proper disposal of earth and garbage.
* Conservation of roads, drains and roadsides.
What are the major features of resettlement?
CEB has indicated the fundamental principles on which the
re-settlement program will be based:
* All settlement will take place within the Talawakelle town limits
and hence within an acceptable distance of their original settlement
areas.
* Each individual sub-community will be offered the opportunity to
resettle together in a clearly defined area, avoiding community
fragmentation and maintaining ethnic balance and existing social
networks.
* All households will be provided with housing and services that are
significantly better than their pre-settlement conditions:
* The settlement plan will be prepared through a process of
consultation with the local communities and with the re-settlement
committee.
What are the direct
benefits to the affected households?
The policy of the Upper Kotmale Hydropower Project is to provide
alternative houses in lieu of all affected houses. Floor area of most
affected houses are less than 300 sq.ft. some of the affected houses are
semi-permanent and without even basic facilities such as electricity,
pipe-borne water and proper access roads. A large number of householders
do not possess any legal titles to the land on which the houses are
built. There are encroachers on the State land.
The project under its Resettlement Policy treats all the affected
households who were in occupation before the cut-off date of June 22,
2001 irrespective of whether they possess legal titles on the land or
not.
The project has made arrangements to provide affected households with
alternative houses with larger floor areas with much improved facilities
such as electricity, pipe-borne water and better access roads. Also the
affected common amenities such as kovils, creches, playgrounds etc. will
be reconstructed at the new re-settlement sites, by the project.
What are the steps
taken by the project to enhance the income of People’s affected?
The National Involuntary Resettlement Policy (NIRP) came in to effect
in 2001 has emphasized that “The livelihood of the displaced person
should be re-established and standard of living improved” without being
restricted to re-establishment of any loss livelihood of the affected
people the Upper Kotmale Hydropower Project has implemented an Income
Enhancement Program (IEP) with a view to improving the income levels of
all the affected households. The IEP includes.
* Training/Occupational Skills Development (OSD) program
The project has conducted the following occupational Skills
Development Training Course for the benefit of the members of the
affected families with a view to assist them to find employment in
relevant fields and to engage in income generating ventures.
* Heavy machinery maintenance
* Electric welding
* Electric wiring
* Plumbing
* Tailoring/Dressmaking
* Mushroom cultivation
* Computer training
* Development of a Micro Credit Scheme
The Upper Kotmale Hydropower Project has initiated action to
establish a revolving fund to provide micro credit facilities to the
member of the affected families, at a very low interest rate enabling
them to engage in income generating activities and thereby to improve
their family income.
* Home gardening
The project has taken steps to launch a homegarden program. Where
every household will be providing with a set of agricultural implement
seeds and fertilizer free of charge required for the first crop.
How is the Project
managed?
Project is the broken down to five lots for easy management.
Lot 1- Preparatory works
Lot 2- Main Civil works
Lot 3- Hydro Mechanical
works
Lot 4- Electro Mechanical
Equipments
Lot 5- Transmission Line
What comes under Lot-1 preparatory work?
* Construction of new access road with drains, culverts and bridges
* Construction of a new bridge (83m length) across Kotmale Oya at
Talawakelle
* Widening and improving existing road Talawakelle - Tawalantenna of
33 km.
* Among the new construction there are 495 houses, 33 shops, 6
workshops, sixlibraries, two churches, 3 kovils across all resettlement
sites.
* A major benefit for the children can be identified in the form of a
new school (Talawakelle Tamil school) of five buildings with modern
facilities such as auditorium, canteen and quarters for the principal.
* Three storeyed Urban Council building with all facilities.
* Modern buildings for rest house, playground and cinema hall in
keeping with standards of film corporation.
* Permanent facilities for the CEB staff and consultant staff.
* New 32 km, 33 kv double circuit distribution lines.
What comes under Lot 2 - Main civil work?
* Construction of concrete gravity dam
Length - 157 m
Height - 35 m
Width - 7 m
* Construction of Tunnel
Length - 12.9 km.
Diametre - 5.8m/4.5m
* Construction of Surgetank 12 m dia. and height 94 m
* Construction of the underground power house complex and switchyard.
What comes under Lot 3 - Hydro
mechanical work?
Design and installation of
* Spillway Radial Gate, stop logs, trash racks
* Embedded tunnel steel liners
* Embedded steel penstock
* Discharge facility for St. Clair waterfall.
What comes under Lot 4 - Electro mechanical equipment
* Design and installation of turbine, generator, power transformer
switchyard equipment, power plant equipment.
* Expansion of Kotmale 220 KV switchyard.
* Expansion of 33 KV Nuwara-Eliya grid substation.
* Flood forecasting system.
What comes under Lot 5 - Transmission
line?
Design and construction of 17.5 km length 220 kv double circuit
transmission line between Upper Kotmale switchyard and Kotmale
switchyard.
Have all the contracts been awarded?
Lot 1 - Contract was awarded on July, 27, 2005 to Maeda Corporation,
Japan.
Lot 2 - Contract was awarded on December 6, 2006 to Maeda Nishimatsu
Joint Venture, Japan.
Lot 3 - Contract was awarded on November 29, 2007 to Kurimoto Ltd,
Japan.
Lot 4 - Bids opened on October 31, 2007.
Lot 5 - Transmission line profile survey completed building documents
under preparation.
What is happening in lot 2 - Main
civil work?
* Concreting of intake dam is in progress
* Headrace and penstock tunnel excavation is ongoing.
* Excavation of power cavern completed first concreting work is in
progress.
* Tailrace tunnel lining is in progress.
* Switchyard banking work is continued.
What are the principal features of
the project?
Run-of-river type with a regulating pond
Water level
Full supply level (FSL) 1,194 mmsl, Minimum Operating Level (MOL)
1,190 mmsl, Normal tail water level 703 mmsl.
Effective strong capacity. reservoir Area, 0.8 MCM, 0.25 KM2, Maximum
plant discharge 36.9 m3/s
Head
Maximum gross head 491m, Net head at full operation 473m, Installed
capacity 150mw, (75mwx2 units), Annual energy 409 gwn, Plant factor 30
percent.
Note: mmsl- metres above main sea level GWH Giga Watt-Hour
(Million units of electricity) MCM Million Cubic Metres. |