Committee to look into low cost power purchase - Ministry of
Power and Energy
Power and Energy Minister W. D. J. Seneviratna has appointed a three
member committee chaired by Prof. R. A. Athalage of the University of
avenues for Moratuwa to explore purchasing electricity units generated
at the Kerawalapitiya Power Plant under the least cost basis. The
construction of Kerawalapitiya Power Plant with a capacity of 300 MW has
been completed in one year, to avoid the electricity crisis anticipated
in 2009.
The Kerawalapitiya Power Plant constructed with technological
contribution of local engineers by West Cost Electricity Company
Limited, affiliated to Lanka Transformer Ltd., which is a CEB owned
Subsidiary Company, generates an electricity of 200 MW at Phase I using
profitable heavy oil. The balance 100 MW is generated using thermal and
will be added to the national grid in 2009 and will be converted to a
natural gas generation plant afterwards.
The committee has been instructed to submit its report within two
weeks and the generation of electricity will begin after the report is
received.
Dr. P. W. Weerasinghe and T. D. Handagama, Deputy General Manager of
the Ceylon Electricity Board function as the other two members of the
Committee.
Meanwhile, work on the new jetty of the 960 mega watt Norochcholai
Coal-powered Generation Project will begin this week, the Power and
Energy Ministry said. The civil engineering component of the manpower
have and other construction works have been completed while the
installation of the transmission line from Puttalam to Veyangoda is in
progress.
Eighty displaced families have been paid compensation and relocated.
The mega project is expected to be completed by 2011, Ministry sources
said.
With the completion of stage I, 300 mega watts will be added to the
national grid in 2011. The total cost of the project is estimated at US$
455 million, the Ministry said. |