Coal power will ensure no black-outs
Walter LIYANARACHCHI in Norochcholai
The Government has taken a firm decision to reinforce the coal power
supply generation to eliminate the off and on poor feeding of
unpredictable hydro power supply due to unhealthy weather changes.
"During the past we have been chiefly depending on hydro power supply
which caused interruptions to the national consumption and especially
disrupting the economy.
The decision to strengthen the coal power generation will be a
solution to the short supply of hydro power due to droughts and to
ensure that there will be no black-outs. Industrialists, entrepreneurs
and various other sources depending on electricity will also not be
hampered", said Ceylon Electricity Board Chairman C.A.S.K. Edirisinghe.
The CEB Chairman was speaking during an inspection tour to the
Norochcholai Coal Power project work site.
The Norochcholai Coal Power plant was planned to be built in three
phases. The construction of the first phase has now been completed 75
percent and 300 MW is expected to feed into the national grid from time
to time on a trial basis in mid June next year.
By the end of the year, the plants will strengthen the national grid
permanently with 300 MW. Earlier it was planned to commence phase two
and three in different periods but considering the national importance
to meet the growing electricity demand and to fall in line with the
Government's expeditious development projects, it has been decided to
complete phase two and three together generating 600 MW in addition to
the 300 MW, Edirisinghe said.
The construction of the first phase power plant was officially
commenced in August 2008. A US $ 455 million loan was secured from the
People's Republic of China through EXIM Bank of China. Lands required
for the construction of the power plant, resettlement and for
improvement of the access roads have been acquired within the past two
years. Resettlement of 80 families in furnished houses was carried out
in Daluwa. The houses of the resettlers were provided with all modern
facilities, sanitary, water, electricity etc., who had lived in
makeshift cadjan houses, the Chairman said.
Project Director (Electrical) P.C.C. Perera said 13 km from Palaviya
to work site was renovated and the balance 40 km upto Kalpitiya will be
rehabilitated with CEB expenses.
The construction of the 150m chimney, boiler and the main generating
plants which are the large scale constructions of the power house is
nearing completion.
Internal roads and other buildings were constructed in parallel and
the three storied administrative building, cafeteria and fire protection
building are also nearing completion.
Approval for the 117 km, 220 KV transmission line from Norochcholai
power house to the Veyangoda Grid sub station had been received and
basic surveying activities and geological surveys have been finalised,
he said.
|